The project is equipped with 2×1025t/h subcritical coal-fired boiler, 2×300MW subcritical steam-extracted condensing turbine generator, an open-cycle seawater cooling system and a limestone FGD system.
The project has a construction period of 13 months, a new record of 300MW units in China, from site leveling to synchronization.