The project is equipped with 2×450t/h CFB boilers, 2×50MW back-pressure turbine generators, 1×1100t/h CFB boiler and 1×300MW steam-extracted condensing turbine generator.
The project adopts a two-level arrangement with a height difference of 12 meters and a 2km long coal conveyor trestle to the powerhouse.